Baseline (tppss0120s000)
Use this session to maintain a baseline (planning) for a project. A baseline stores the start and end dates of each activity of the activity-structure.
These start and end dates can be created in these ways:
- Manual entry in the Activities (tppss2100m000)session
 - Result from network planning
 - Be created from a particular schedule in the external scheduling package.
 
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Description
 - 
            
The description or name of the code.
 - Status
 - Baseline
 - Details
 - 
            
- Description
 - 
                     
The description or name of the code.
 - Baseline Status
 - 
                     
The status of the current baseline.
Allowed values
- Free
 - 
               
The baseline is created.
 - Approved
 - 
               
The baseline is approved.
 
Note: The baseline data cannot be updated after the baseline status is Approved. - Approval Date
 - 
                     
The date and time of approval of the baseline.
 - Baseline Start Date
 - 
                     
The earliest possible start date and time of the baseline. This value is displayed based on the Activity Baseline (tppss2120m000) session.
 - Baseline Finish Date
 - 
                     
The latest possible finish date and time of the baseline. This value is displayed based on the Activity Baseline (tppss2120m000) session.
 - Derived from Baseline
 - 
                     
The baseline from which the current baseline is derived.
 - Tracking
 - 
                     
- Creation Date
 - 
                              
The date and time of creation of the baseline.
 - Date of Last Update
 - 
                              
The date and time the baseline was last updated.
 - Last Modified by
 - 
                              
The name of the user who last modifies the baseline.
 
 
 - Text
 - 
            
If this check box is selected, a text is present.