Revenue Surcharges by Cost Component (tpppc2586m000)

Use this session to list revenue surcharges for a combination of the project, the cost component, and the surcharge code.

Note: If you have started this session by zooming, you can only find and select a record.

Field Information

Project

The code that identifies the project.

Project Status

The project status.

Cost Component

The cost component code on which the surcharge must be calculated.

Sundry Cost

The sundry costs code

Sequence Number

The sequence number code.

Percentage

The surcharge percentage specified for the cost to calculate the surcharge amount.

Posting Method Finance

Indicates the process to post surcharges to Financials , following the registration of costs and revenues.

Element

The element code to which the calculated surcharge must be posted. If you leave this field blank, the surcharge is posted to the element under which the cost, on which the surcharge is calculated, has been recorded.

Cost Component (Control)

The cost component code to which the surcharge is posted. If you leave this field blank, the surcharge is posted to the cost component that contains the costs on which the surcharge is calculated.

Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.