Sundry Cost Forecast (tpppc2196s000)
Use this session to maintain cost forecast for the combination of the project and the registration date for different sundry-cost codes.
These values are used to compute forecast amounts in control enquiries and report sessions.
Field Information
- Project
 - 
            
The project code.
 - Description
 - 
            
The description or name of the code.
 - Status
 - 
            
The project status.
Allowed values
- Free
 - Active
 - Finished
 - Closed
 - Archived
 
 - Cost Component
 - 
            
The cost component.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Registration Date
 - 
            
The date of input for the forecast deviation of costs.
 - Cost Object Details
 - 
            
- Element
 - 
                     
The element code.
 - Description
 - 
                     
The description or name of the code.
 - Element Status
 - 
                     
The work authorization status of the element.
Allowed values
- Free
 - On Hold
 - Released
 - Finished
 - Closed
 
 - Activity
 - 
                     
The activity code.
 - Description
 - 
                     
The description or name of the code.
 - Activity Status
 - 
                     
The work authorization status of the activity.
Allowed values
- Free
 - On Hold
 - Released
 - Finished
 - Closed
 
 - Description
 - 
                     
The description or name of the code.
 - Sundry Cost
 - 
                     
The sundry costs code.
 - Description
 - 
                     
The description or name of the code.
 - Unit Cost Currency
 - 
                     
The currency in which unit cost is expressed.
Note: This field is disabled if the Final Rate checkbox is selected. - Unit Cost
 - 
                     
The unit cost per unit.
Note: This field is disabled if the Final Rate checkbox is selected. - Final Rate
 - 
                     
If this check box is selected, the Unit Cost is considered as the final cost rate.
Note:- If the forecast amount is modified with the Final Rate checkbox cleared, Infor LN recalculates the Unit Cost.
 - If the forecast amount is modified with the Final Rate checkbox selected, Infor LN recalculates the Forecast Quantity.
 
 - Currency Rate/Rate Factor
 - 
                     
The rate that belongs to the currency rate that is displayed.
 - Rate Factor (Costs)
 - 
                     
The rate factor.
 - Text
 - 
                     
If this check box is selected, a text is present.
 
 - Cost
 - 
            
- Budget
 - 
                     
The total budget amount.
 - Quantity
 - 
                     
The total quantity of the sundry cost object budgeted for the element or activity.
 - Earned Value
 - 
                     
The performed amount.
 - Physical Progress
 - 
                     
The progress percentage.
 - Actual
 - 
                     
The actual amount spent.
 - Quantity
 - 
                     
The actual quantity of the sundry cost object specified on the cost line.
 
 - Forecast
 - 
            
- Forecast Quantity
 - 
                     
The quantity on which the forecast cost variance is based.
 - Forecast Quantity Unit
 - 
                     
The unit in which the forecast quantity is expressed.
 - Cost Amount
 - 
                     
The total sundry costs. If you change the generated cost amount, the unit-cost rate is automatically adjusted.
 - Cost Amount
 - 
                     
The home currency in which cost amount is expressed.
 - 
                     
The cost amount in the home currency.
 - Estimated Extra Costs
 - 
                     
The amount you enter here is the estimated extra costs on top of your already estimated budget.
Note: You can view this field only if the Leading Forecast Method field is set to Estimated Extra Costs in the Project Accounting Parameters (tpppc0100s000) session. - Estimate to Complete
 - 
                     
The estimate to complete value is the expected additional cost needed to complete an activity or project.
Note: You can view this field and is enabled only if the Leading Forecast Method field is set to Estimate to Complete in the Project Accounting Parameters (tpppc0100s000) session. - Estimate at Completion
 - 
                     
The Estimated Cost at Completion value is used to determine what the cost is at the end of a project.
Note: You can view this field and is enabled only if the Leading Forecast Method field is set to Estimate at Completion in the Project Accounting Parameters (tpppc0100s000) session. - Approved
 - 
                     
If this check box is selected, the forecasted cost amount is approved. Only approved cost forecast reports are considered for cost control and interim results.
Note: After the forecasted amount is approved, LN does not allow you to modify the forecast data. 
 - Variance
 - 
            
- Variance
 - 
                     
The project result.
 - Forecast Variance
 - 
                     
The forecast result.