Cost Forecast by Activity/Cost Type (tpppc2126m000)

Use this session to maintain the cost forecast for the combination of project, registration date, and activity for the different cost types. This data is used to calculate the extra costs and estimate to complete or estimate at completion amount in the performance measurement sessions.

Note: To add records or to generate a forecast using this session, you must have a top-down budget version that is valid for the registration date.

Field Information

Project

The project code for which the cost forecast is maintained.

Description

The description or name of the code.

Project Status

The project status of the project for which the cost forecast is maintained.

Registration Date

The date of input for the forecast deviation of costs. Based on the registration date, Infor LN determines on which actual transaction must be considered for the calculation of the forecast. For example, if there are two actual cost transactions with date October 15 and another with October 20 and the specified registration date of the forecast is before October 20 and after October 15, the one with date October 20 is ignored.

Activity

The activity code for which the cost forecast is maintained.

Description

The description or name of the code.

Currency

The currency in which the cost forecast is maintained.

Currency Rate/Rate Factor

The currency rate that is used to convert the transaction currency to the home currency.

Rate Factor

The rate factor that belongs to the currency rate which is displayed.

Material

The estimate to complete amount needed for the item cost type to finish the project.

Labor

The estimate to complete amount needed for the labor cost type to finish the project.

Equipment

The estimate to complete amount needed for the equipment cost type to finish the project.

Subcontracting

The estimate to complete amount needed for the subcontracting cost type to finish the project.

Sundry Cost

The estimate to complete amount needed for the sundry cost's cost type to finish the project.

Home Currency

The cost amount in the home currency. Click Rotate Currency to see the amount in the other home currencies.

Material

The amount of the material in home currency. Click Rotate Currency to see the amount in the other home currencies.

Labor

The amount of the labor in the home currency. Click Rotate Currency to see the amount in the other home currencies.

Equipment

The amount of the equipment in home currency. Click Rotate Currency to see the amount in the other home currencies.

Subcontracting

The amount of the subcontracting in home currency. Click Rotate Currency to see the amount in the other home currencies.

Sundry Cost

The amount of the sundry cost in home currency. Click Rotate Currency to see the amount in the other home currencies.

Material

The estimate at completion amount for the material cost type.

Labor

The estimate at completion amount for the labor cost type.

Equipment

The estimate at completion amount for the equipment cost type.

Subcontracting

The estimate at completion amount for the subcontracting cost type.

Sundry Cost

The estimate at completion amount for the sundry cost type.

Material

The cost of the material in home currency. Click Rotate Currency to see the amount in the other home currencies.

Labor

The cost of the labor in home currency. Click Rotate Currency to see the amount in the other home currencies.

Equipment

The cost of the equipment in home currency. Click Rotate Currency to see the amount in the other home currencies.

Subcontracting

The cost of the subcontracting in home currency. Click Rotate Currency to see the amount in the other home currencies.

Sundry Cost

The cost of the sundry cost in home currency. Click Rotate Currency to see the amount in the other home currencies.

Actuals for Item

The actual amount for material cost type.

Actuals for Labor

The actual labor amount.

Actuals for Equipment

The actual equipment amount.

Actuals for Subcontracting

The actual subcontracting amount.

Actuals for Sundry Cost

The actual sundry cost amount.

Material

The budgeted amount for the material cost type .

Labor

The budgeted labor amount.

Equipment

The budgeted equipment amount.

Subcontracting

The budgeted subcontracting amount.

Sundry Cost

The budgeted sundry cost amount.

Currency

The estimate at completion amount in home currency.