Physical Progress by Extension/Cost Type (tpppc1589m000)

Use this session to display progress of an extension at the cost type level.

Field Information

Project

The project code.

Project Status

The project status.

Date

The date for which forecast will be generated.

Extension

The extension code.

Material

The progress percentage for the item cost object.

Labor

The progress percentage for the labor cost object.

Equipment

The progress percentage for the equipment cost object.

Subcontracting

The progress percentage for the subcontracting cost object.

Sundry Cost

The progress percentage for the sundry costs cost object.