Activity Physical Progress (tpppc1560m000)

Use this session to list the progress of activities for a project.

Note: If you have started this session by zooming, you can only find and select a record.

Field Information

Project

The project code.

Description

The description or name of the code.

Project Status

The project status.

Date

The date for which forecast will be generated.

Activity

The activity's code.

Description

The description or name of the code.

Work Authorization Status

The work authorization status of the activity.

Physical Progress Quantity

The budgeted number of activities. The progress is compared with this quantity.

Unit

The unit defined for the activity in the Activities (tppss2100m000) session.

Cumulative [Quantity]

The number of activities to be invoiced.

Cumulative [%]

The total progress for this activity, as a percentage.

Reported Completed

If this check box is selected, the production of the selected activity is completed. You can still enter the progress.

Approved

Indicates that the physical progress of the activity is approved.

Note: 
  • Activity progress that is approved cannot be modified or deleted.
  • Progress invoice installments can be generated only for approved activity progress using the Create Progress Invoice Installments (tppin1210m000) session.
  • Approved activity progress which is invoiced cannot be disapproved (Unapprove).
Text

If this check box is selected, a text is present.