Assignments Cost Base (tppdm2120m000)
Use this session to define the cost types, cost components or cost objects for the selected project for which overheads must be calculated.
Field Information
- Base
 - 
            
The code that uniquely identifies the overhead application base.
 - Version
 - 
            
The Version number of the corresponding base-code for the overhead application.
 - Exclude
 - 
            
If this check box is selected, the enterprise unit, program, project-group or project, within the specified range are excluded from the overhead calculation and application.
 - Cost Type
 - 
            
The cost type for which the overhead cost is applied and calculated.
Allowed values
- Labor
 - 
               
The overheads are calculated for Labor cost type.
 - Overhead
 - 
               
The overheads are calculated for Overhead cost type.
 - Materials
 - 
               
The overheads are calculated for Material cost type.
 - Equipment
 - 
               
The overheads are calculated for Equipment cost type.
 - Subcontracting
 - 
               
The overheads are calculated for Subcontracting cost type.
 - Sundry Costs
 - 
               
The overheads are calculated for Sundry cost type.
 
Note:- If the field Base Type in the Overhead Application Base (tppdm2600m000) session is set to Direct Labor Hours, only Labor is available in the field Cost Type.
 - The Overhead option is not visible if the value in the field Level is 1.
 
 - Cost Component From
 - 
            
The From and To fields define a range of: cost components for which the overhead costs are calculated.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Cost Object From
 - 
            
The From and To fields define a range of: cost objects for which the overhead costs are calculated.