Cost Peg Audit History (tpctm2500m000)

Use this session to view the history data of the project cost peg. You can also view the changes to the project peg data; when you add, modify, and delete the project peg data of the orders.

Note: 
  • You can access this session only if the Manual Project Peg Modification check box is selected in the Project Pegging Parameters (tcpeg0100m000) session.
  • The Purchase Requisition History and Request for Quotations History options are visible, only if the Requisitions and Requests for Quotation options are selected in the Procurement Parameters (tdpur0100m000) sessions.
  • The Re-export Transfer and Re-export Transfer History options are displayed in the Reference Menu only if the End User Statements check box is selected in the Trade Management Parameters (tcgtc0100m000) session.

Field Information

Order Type

The order type for which project peg data is updated when you add, modify or delete the project peg manually.

Allowed values

Not Applicable
Cycle Counting Order
Maintenance Sales Order
Purchase Requisition
Request for Quotation
Purchase Order
Purchase Schedule
Production Order
Cost Peg Transfer
Warehouse Transfer (Manual)
Warehouse Project
Warehouse Project (Manual)
Adjustment Order
Order

The order number for which the project peg history data is displayed.

Transaction Type

The transaction types for Warehouse Transfer (Manual) and Cost Peg Transfer origin transactions are Inbound and Outbound.

Order Line

The position number of the order line for which project peg data is displayed.

Order Line Reference

The reference number of the order line for which project peg data is displayed.

Distribution Line

The sequence number of the project peg distribution line.

Old Project

The code of the project, before the project peg data is modified.

Item

The code of the item that is linked to the project.

Effectivity Unit

The code of the effectivity unit of the item, linked to the project.

Old Element

The code of the element linked to the project, before the project peg data is modified.

Old Activity

The code of the activity linked to the project, before the project peg data is modified.

Project

The project code of the modified project peg.

Element

The code of the element linked to the modified project.

Activity

The code of the activity linked to the modified project.

Old Quantity

The quantity of the project peg, before the project peg data is modified.

Unit

The inventory unit in which the quantity of the project peg data is expressed.

New Quantity

The modified project peg quantity.

Old Project Peg Origin

The origin of the project peg, before the project peg data is modified.

Allowed values

Costing Break
Not Applicable
Manual
Top Demand
Project Peg Origin

The origin of the modified project peg.

Allowed values

Costing Break
Not Applicable
Manual
Top Demand
Change Reason

The reason code specified for modifying the project peg data.

Note: You can only view the reason code of the type Project Peg Audit History.
Contract

The contract to which the project is linked.

Contract Line

The contract line number.

Change Type

The type of change performed on the project peg data.

Allowed values

Created

When a project peg is created.

Modified

When a project peg is modified (activity or quantity).

Deleted

When a project peg is removed.

None

When only the peg distribution data is modified and the peg data remains unchanged. Example, for a purchase order, the peg distribution of only one order line is modified. The data for the other related lines remains unchanged.

All Types

The cost peg audit history data is displayed for all the change types.

Project Peg Audit

The specific peg distribution data that is modified.

Allowed values

Project

When the project of the peg distribution is modified, this value is displayed.

None

When the project peg data is not modified, this value is displayed.

Project Peg

When the element and/ or activity of a project peg line is modified, this value is displayed.

Quantity

When the quantity of an item of the project peg is modified, this value is displayed.

Modified by

The code of the user who adds, modifies, or deletes the project peg data.

User name

The name of the user who adds, modifies, or deletes the project peg data.

Modified on

The date on which the project peg data is added, modified, or deleted.