Job Shop Planning Board

A shop floor planner can use the Job Shop Planning Board (tisfc8372m000) to manually change the schedule of operations for balancing the supply and demand.

The schedule of operations can also be changed manually when:

  • A machine breaks down
  • Labour force restrictions
  • Important customer wants priority
  • Purchase or supply of a part is running late

Infor LN defaults the Site in this session from the Production User Profiles (timfc0120m000) session if the multisite functionality is implemented.