Update check Planned by Planner Consistency

In the Items - Ordering (tcibd2100m000) session you can select the Planner check box to indicate that an item must be planned by Supply Chain Planner instead of by Manufacturing Resource Planning (MRP) in Enterprise Planning.

You can only do this if the following two conditions are met:

  • Supply Chain Planner is installed
  • The item's Order System that is defined in the Items (tcibd0501m000) session is Planned

If both a parent item and a child item in the BOM are marked as Planned by Infor Planning, Exploded by SCS Planner must be selected for the child item's BOM line.

However, you can change the Planned by Infor Planning status of an item after a BOM line is inserted, which means that Exploded by SCS Planner may be cleared. Use Check Planned by Planner Consistency (tibom1210m000) to check the consistency of the BOM explosion, and to update the Exploded by SCS Planner status of a BOM line.