Subcontracting Bill of Material (tisub1110m000)

Use this session to manage subcontracting bill of material (BOM)

Field Information

Product

The subcontracted item.

Subcontractor

subcontractor

Subcontractor Site

The ID of the site where subcontracted work is performed.

Ship-from Business Partner

The business partner who ships the subcontracted part.

Revision

The revision ID.

Site

The site ID.

Note: Only visible if multisite functionality is active.

Position

The subcontracted item's position number.

Material

The item that is a component of the received main item.

Supplied by Subcontractor

If you subcontract one or more operations, or an item's entire production process, you can choose whether or not to send material to the subcontractor to use for the subcontracted item.

  • If this check box is selected, the material is not sent to the subcontractor. The material is supplied by the subcontractor.
  • If this check box is cleared, and the material is linked to a subcontracted operation, the material is sent to the subcontractor.

Net Quantity in BOM Unit

The net quantity to be specified in BOM unit. To use a BOM unit that is other than the item unit, there must be an approved conversion factor. If the item unit is different than the BOM unit, the net quantity in item unit is calculated based on the approved conversion factor.

Note: This field is enabled only if:
  • The BOM Units of Material Lines check box is selected in the Product Engineering Parameters (timfc0100m000) session.
  • The Use BOM Units check box is selected in the Product Subcontractors List (tisub1100m000) session.
  • The Status of the Product Subcontracting Model is set to New.
Net Quantity

The number of items on the BOM line to which the reference designator applies. A reference designator can apply to one or more items on the BOM line.

BOM Unit

The unit in which the related Net and Scrap quantities are expressed.

Note: This field is enabled only if:
  • This field is enabled only if:
    • The BOM Units of Material Lines check box is selected in the Product Engineering Parameters (timfc0100m000) session.
    • The Status of the Production Bill of Material is set to New.
  • If the Use Bom Units check box is selected, the value specified for the BOM Unit is defaulted to the value of the item unit.
Scrap (%)

The percentage of material that is lost during production.

Warehouse

The warehouse from which materials are shipped to the subcontractor.

Supply System

The supply system used.

Lot Selection

The lot code of the product.

Inherit Demand Peg

If this check box is selected, the dependent components will inherit the project peg of the main item.