Production Schedule Line (tirpt4602m100)

Use this session to analyze a schedule line and related data.

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Production Schedule

The ID of the scheduled production line.

Item

The repetitive item that is being reported.

Work Cell

work cell

Repair Cell

repair cell

Origin

View the origine of the manufacturing request.

Allowed values

Planning

The production run is scheduled using Enterprise Planning .

Manual

The production run is scheduled manually.

Original Start

The earliest date materials to manufacture the item are available.

Original Finish

The earliest date the planned quantity can be completed.

Planned Start

The planned start date for the production of the item.

Planned Finish

The planned finish date for the production of the item.

Actual Start

The date production started.

Actual Finish

The date production finished.

Ordered

The quantity to be produced.

Completed

The quantity that is already been completed.

To Backflush

The quantity to backflush.

Backflushed

The quantity product for which materials are backflushed.

Warehousing Order

The warehousing order for the material to be issued.

Note: If product from the schedule line is quarantined, the warehousing order can be used as a quarantine receipt.

Rejected

The quantity product rejected during production. You must decide if the quantity is scrapped, moved to quarantine or to a repair cell.

Scrapped

The quantity product scrapped during production.

Quarantined

The quantity quarantined during production.

To Repair

The quantity still to be repaired.

Repaired

The quantity of product repaired during production.