Data Selection for Planning Board (tipcs4171m000)
Use this session to indicate planning board related selections, which give you insight into the relationships between activities.
For example
- Choose if you want to make the selections on a project or on an activity level.
 - Select a planning board group.
 - Make the settings that relate to the presentation of the planning board, such as, sort of activities, type of start date and type of activities.
 
Field Information
- Project
 - Project Employee
 - 
            
The person that is involved in the execution of the project.
 - Status
 - 
            
Indicates the current progress of the project.
 - Start Date
 - 
            
The date the project is started.
 - Completion Date
 - 
            
The day the project is completed.
 - Activity
 - 
            
The activity in the network planning for a project.
 - Search Key
 - Activity Manager
 - Earliest Start Date
 - 
            
The earliest date an activity can start, taking into account previous and next activities and the company calendar.
 - Planning Board Group
 - 
            
Contains all settings with respect to displaying objects, their colors, the date scale, and so on.
 - Sort by
 - 
            
Use this field to determine how the activities are to be sorted on the planning board.
 - Start Dates Activities
 - 
            
Allows you to indicate how the activity should be shown: starting from the earliest start date OR from the latest start date.
 - Show Also Completed Activities
 - 
            
If this check box is selected, all the activities are displayed (including completed activities).
If this check box is cleared, only incomplete activities are displayed.