Copy Standard Product Structure to Customized Structure (tipcs2230m000)
Use this session to copy a standard product structure, to a customized structure to support the project engineering for customer order-related customized production.
Field Information
- Site
 - 
            
The site ID of the original site.
 - Source
 - 
            
- Standard Item
 - 
                     
Enter the code of the standard item for which you want to copy the product structure to a project. This code must have been predefined in the Items (tcibd0501m000) session.
 
 - Target
 - 
            
- Customized Item
 - 
                     
Enter the code of the customized item to which the standard item must be copied.
 
 - Reference Date
 - 
            
- Use Reference Date of the Project
 - 
                     
If this check box is selected, the reference date field is disabled as the reference date is derived from the source project. If the source project does not have a reference date, LN will select the system time.
 - Effectivity Unit
 
 - Unit Effectivity
 - 
            
- Copy all components and all effectivity statements
 - 
                     
If this check box is selected, unit effectivity is copied from a standard product structure to a customized structure. You can fill in the unit for which you want to copy unit effectivity. Exceptions are copied for routings and routing operations that fulfill the date effectivity conditions.
 - Copy only components valid for Effectivity Unit
 - 
                     
The date in this field determines that only those parts of the project structure are copied that are valid on the date specified.
 
 - Options
 - 
            
- Copy Product Structure
 - 
                     
In this field you can choose to copy the entire product structure or only its first level, or to make the copying process interactive.
Allowed values
- 
                           
Single Level
Only the first level of the production structure is copied. - 
                           
Multilevel
All levels of the product structure are copied. - 
                           
Interactive
You will be prompted to select which levels are copied. 
 - 
                           
 - Copy Items
 - 
                     
Using this field, you can define whether to copy only standard-to-order items, both standard-to-order items and anonymously manufactured items, or all items.
Allowed values
- Customizable Items
 - All Items
 
 - Copy E-Item Relationships
 - 
                     
If this check box is selected, the E-item relationships are copied to the customized structure.
 - Alternative Material
 - 
                     
If this check box is selected, the alternative materials of the BOM components are copied as well.
If this check box is cleared, the copying process ignores the alternative materials.
 - Use Up Material
 - 
                     
If this check box is selected, the use-up materials of the BOM components are copied as well. If this check box is cleared, the copying process ignores the use-up materials.
 - Generate New Item Codes when Customized Item exists
 - 
                     
LN generates a new item code when a customized item is filled in.
 - Ask before Generating New Item Code
 - 
                     
Whenever a new item code is generated, LN will ask you to confirm this action.
 - Approve Conversion Factors
 - 
                     
If this check box is selected, LN approves the conversion factors for the item.
 - Copy Testing Combinations
 - 
                     
If this check box is selected, option combinations used for testing are copied along with the item.