Replace Item in Production Bill of Material (timfc3200m300)
Use this session to replace items in the production bill of material with a new item.
A report is printed containing the changes made in this session.
Note:
-
If an item in a production bill of material with the status Approved and Expired is replaced, a new revision of the production bill of material is generated with the status New.
-
To use this session the Job Shop by Site parameter in the Concept Activation (tcemm4600m000) session must be set to Active or In Preparation.
Field Information
- Item to be Replaced
-
The material or component to be replaced.
- Replacement Item
-
The material or component with which the item will be replaced.
- From Product
-
The product range for which the item is replaced.
- Revision
-
The revision range for which the item is replaced.