Production Bills of Material (timfc3100m000)

Use this session to manage production bills of material.

Using the P-BOM product can be manufactured in the job shop, subcontracting or repetitive manufacturing.

Note: Infor LN allows you to modify a field on the production bill of material header with a status of New only if:
  • The Product Lifecycle Management (PLM) is not the origin of the production bill of material.
  • You can manually modify the PLM Controlled fields based on the settings defined in the Production Bill of Material Control (timfc3199m000) session.
  • The field is not controlled by PLM based on the template defined in the Production Bill of Material Control (timfc3199m000) session.

For the production bill of material that originates from Product Lifecycle Management (PLM), you can create a new revision using the New Revision option from the Actions menu only if the Manual Add Revision check box is selected in the Production Bill of Material Control (timfc3199m000) session.

Note: To use this session the Job Shop by Site parameter in the Implemented Software Components (tccom0100s000) session must be set to Active or In Preparation.

Field Information

Product

The product for manufacture.

Revision

The revision of the bill of material.

Status

The status of the production bill of material.

Allowed values

  • New
  • Approved
  • Expired
BOM Quantity

BOM quantity

Use BOM Units

If this check box is selected, you can specify a BOM unit for the material lines. The item quantity can be specified in a unit other than the item unit.

Note: 
  • By default, this check box is cleared.
  • This check box is enabled only if:
    • The Status of the Production Bill of Material is New.
    • The BOM Units of Material Lines check box is selected in the Product Engineering Parameters (timfc0100m000) session.
Effective Date

The date the production bill of material becomes effective.

Expiry Date

The date the production bill of material is no longer effective.

Created By

The name of the employee responsible for the creation of the PBOM.

Created On

The date the PBOM was created.

Approved By

The employee responsible for the approval of the production bill of material.

Approved On

The date the production bill of material was approved.

Expired By

The eployee responsible for expiring the production bill of material.

Expired On

The date the production bill of material was expired.

Text

If this check box is selected, a text is available.

Source

The origin of the P-BOM.

Allowed values

Manual

The P-BOM is defined in the Production Bills of Material (timfc3100m000) session.

Production Bill of Material

The P-BOM revision was generated from an existing production bill of material.

Engineering Bill of Material

The P-BOM is generated from an engineering bill of material.

Note: If the P-BOM is generated from an E-BOM, the Source Engineering Item and Source Revision fields are filled.
PLM

The P-BOM is generated from data imported from PLM.

Configurator (PCF)

The P-BOM is generated from data imported from the PCF configurator.

Configurator

The P-BOM is generated from data imported from Infor Configurator.

Job Shop Bill of Material

The P-BOM was generated from a job shop bill of material.

Not Specified
Note: These options are not applicable:
  • Configurator (PCF)
  • Configurator
  • Job Shop Bill of Material
  • Not Specified
Source Engineering Item

The item for which the Engineering Bill of Material is defined.

Note: If the P-BOM is created by EDM based on an engineering item- Item Relationship, this field specifies the engineering item.

Source Revision

The revision of the engineering item bill of material.