Print Estimated vs. Actual Material Costs (ticst0401m000)
Use this session to print a report that compares the estimated material costs and the actual material costs for a production order.
Select the range of production orders for which you want to print the costing data. Then indicate:
- If you also want to print the material costs by (costing) work center.
 - If only closed orders must be printed.
 - If LN must recalculate the estimates on basis of the progress of the order.
 
Field Information
- Site
 - 
            
The site ID.
Note: Only visible if multisite functionality is active. - Costing Work Center
 - Group by
 - 
            
Specify if and how the costs are grouped, by work center, or by costing work centers.
 - Currency for details
 - 
            
Select in which currency the costs must be printed.
Note:- If the Currency System of your company is Single or Dependent, this field is enabled.
 - If the Currency System of your company is Independent, this field is disabled and displays Reference.
 
 - Currency for totals
 - 
            
LN prints the cost amounts in this currency.
Note:- In the Currency for details field you can select in which currency the costs must be printed.
 - If you select Currency Total in the Currency for details field, you can enter a currency in this field.
 
 - Print only if actual costs are higher then
 - 
            
Production orders are printed on the report if the production order's total actual material costs are higher then the specified estimated costs' percentage.
 - Print only if actual costs are lower then
 - 
            
Production orders are printed on the report if:
- The production order's total actual material costs are lower then the specified estimated costs' percentage.
 - The production order's status is at least Production Completed.
 
Low costs can indicate costs that were incorrectly registered, for example, if backflushing is forgotten.
Note: If this check box is selected, production orders that are Active, Released, or Created are never printed. - Print corrected Estimates (based on progress)
 - 
            
If this check box is selected, LN corrects the calculated estimates on basis of the quantities reported in the order planning.
 - Print Closed Orders Only
 - 
            
If this check box is selected, LN only prints production orders with the Closed status.
 - Actual Closing date
 - 
            
Production orders are printed on the report if they are closed within the specified date range.
 - Include Supplied by Subcontractor
 - 
            
If this check box is selected, then estimated materials that are supplied by the subcontractor will be printed.
 - Include Customer Owned
 - 
            
If this check box is selected, the customer owned estimated materials will be printed.
 - Include Print Only
 - 
            
If this check box is selected, estimated materials with Material Control Method Print Only will be printed.