Print Multilevel Cost Calculation (ticpr2420m000)

Use this session to print calculations of standard costs and valuation prices for each level of a manufactured item's product structure. The printed calculation is identical to the calculation that is carried out if you run the Calculate Standard Cost (ticpr2210m000) session while the Standard Cost Calculation Method field is Top-Down.

You can print calculations of simulated standard cost/valuation prices as well. Note that this session never updates the standard cost tables.

Field Information

Selection Range
Cost Calculation Code

price calculation code

Item

item

Effectivity Unit

effectivity unit

Calculation Date

The date for which you want to print standard cost calculation data.

The standard cost calculation date is important to simulate cost/valuation price calculations on a date other than the current date. It can lie in the future or in the past. On the basis of this date, LN automatically simulates the structure of the product and the routing as they exist on the given cost calculation date. By default, LN shows the current date.

Enterprise Unit

The enterprise unit, or range of units for which the standard cost calculation is printed.

Note: Only visible if Standard Cost by Enterprise Unit in the Implemented Software Components (tccom0100s000) session is Active.
Settings
Calculation Options
Predefined Order Quantity Main Item

If this check box is selected, LN bases the standard cost calculation on the predefined order quantity of the main item.

If this check box is cleared, you must enter a value in the Use Order Quantity field on which LN bases the standard cost calculation.

  • Predefined order quantity

    LN retrieves the predefined order quantity from the Items - Ordering (tcibd2100m000) session, by selecting the value of one of the following fields:

    • Order Quantity Project
    • Recommended Order Quantity Project

    LN selects the applicable quantity by using the procedure described below.

  • Project items

    If the item code's project segment contains a project, the item is a project item.

    For project items, the predefined order quantity is determined as follows:

    • If the value of the Order Quantity Project field is greater than zero, that quantity is the predefined order quantity.
    • Otherwise, the value of the Recommended Order Quantity Project field is the predefined order quantity.
Use Order Quantity

The order quantity of the main item on which the standard cost calculation is based. You can only enter a value if the Predefined Order Quantity Main Item check box is not selected.

Predefined Order Quantity Sub Items

If this check box is selected, the standard costs and valuation prices of the subitems are based on the predefined order quantity of the sub items. If this check box is cleared, the quantity of the sub items on which LN bases the standard cost calculation is derived from the quantity of the main item.

Example

    Quantity Predefined Order Quantity
Main Item Bicycle 1x 5
Subitem Wheel 2x 15
Subitem ... ... ...
Predefined Order Quantity Sub Items check box Result
Selected

DefaultStandard cost of Wheel based on 15 items is: 100

Standard cost of Main Item:

  • 2x Wheel at 100 = 200
  • ...
Cleared

DefaultOrder quantity of Wheel is 5 x 2= 10

DefaultStandard cost of Wheel is based on 10 items: 105

Standard cost of Main Item

  • 2x Wheel at 105 = 210
  • ...
Note: This check box only applies to standard cost and valuation prices that are calculated with price calculation codes other than the standard cost calculation code in the Standard Cost Calculation Parameters (ticpr0100m000) session.
Details by Cost Component

If this check box is selected, the details of the standard cost and valuation price calculation are printed by cost component.

Include Fixed Costs

If this check box is selected, costs such as operation rates or surcharges that you defined as fixed costs are printed.