Purge and Renumber Sequences (tiasl4201m000)
Use this session to remove assembly orders for a range of assembly lines from the line sequence. If an assembly order is purged from the line sequence, actual sequences are no longer present for the assembly order.
Field Information
- Roll-off Line
 - 
            
Select the roll-off lines from which the assembly order must be purged. Orders that are purged will automatically be purged from all supply lines.
Note: A supply line may be a roll-off line (e.g. for spare parts). To purge these (spare part) orders, their roll-off line must be selected. - Upto Date
 - 
            
The offline date of the assembly order. Only positions with the planned end time on the last segment of the roll-off line before this date are purged.
Note:- 
                     
If a position has an assembly order, its planned end time equals that of the planned offline date of the order.
 - 
                     
Positions are only purged if all other conditions were met.
 
 - 
                     