Application for Payment Lines (tdpur6121m000)
Use this session to maintain the AFP-lines.
Note: 
      
- You can access this session only if the Services Procurement field is set to Active or In Preparation in the Implemented Software Components (tccom0100s000) session.
 - You can access this session only if theServices Procurement Orders check box is selected in the Procurement Parameters (tdpur0100m000) session.
 - You can modify the applied values only if:
- the AFP status is Initiated or Awaiting and the current date is equal to or later than the assessment as at date.
 - The status is Received, In Process or Assessed.
 
 - When an AFP is created, data is defaulted from the related Subcontracting Procurement Order Line (tdpur6601m000) session. The related SPO lines and call-off lines are copied.
 
Field Information
- Application for Payment
 - The code of the Application for Payment.
 - Number
 - The number of the Application for Payment.
 - Status
 -  
					
The Status of the Application for Payment.
Allowed values
- Awaiting
 - Initiated
 - Received
 - In Process
 - Assessed
 - Approved
 - Canceled
 - Closed
 - Not Applicable
 
 - Services Procurement Order
 - The services procurement order number.
 - Line
 - The order line payment number of application related to
						the subcontractor.Note: This value must exist in the Subcontracting Procurement Order Line (tdpur6601m000) session for the related Subcontracting Procurement Order.
 - Sequence
 - The application for payment line number.Note: This value must exist in the Subcontracting Procurement Order Line (tdpur6601m000) session for the related Subcontracting Procurement Order.
 - Variation Line
 - The variation line number linked to the application for payment.
 - Call-Off Line
 - The call off line number of application for
							payment.Note: This value must exist in the Subcontracting Procurement Order Line (tdpur6601m000) session for the related Subcontracting Procurement Order.
 - Assessment
 - 
					
 - Scope of Work
 - 
					
- Description Only
 - Indicates if only the description is specified and not the Scope of Work and item.
 - Scope of Work
 - The scope of work specified for the Supply Type of the Services Trade linked to the related Subcontracting Procurement Order.
 - Line Type
 - The code of the line type.
Allowed values
- Amount Only
 - Rate Only
 - Quantity and Rate
 - Not Applicable
 
 - Quantity
 - The ordered quantity.
 - The unit in which the Quantity is expressed.
 - Procurement Rate
 - The Subcontracting Procurement Order Rate for the
									procured services.Note:
- This value is defaulted from Subcontracting Procurement Order Line (tdpur6601m000) session.
 - This field is enabled only if AFP status is set to Awaiting.
 
 - Currency
 - The currency in which the Procurement Rate is expressed.
 - Procurement Rate Unit
 - The unit of measure for the Procurement Rate.
 - Net Order Amount
 - The net order amount in the Subcontracting Procurement Order Line (tdpur6601m000) session.
 - Capped Amount
 - Indicates the maximum amount that can be invoiced for the order line.
 
 - Previous Periods
 - 
					
- Applied Quantity
 - The applied quantity to previous period.
 - Quantity Unit
 - The unit in which the applied quantity is expressed.
 - Certified Quantity
 - The cumulative Certified Quantity (approved CFP quantity of earlier AFPs).
 - Payless Quantity
 - The balance quantity after deducting assessed
									quantity from the applied quantity. 
Formula: Payless Quantity = Applied Quantity – Assessed Quantity. - Remaining Quantity
 - The remaining quantity after deducting Applied
									Quantity Previous Periods from the Ordered quantity.
										
Formula: Remaining Quantity = Ordered quantity – Applied Quantity Previous Periods. - Applied Amount
 - The applied amount for the line order.
 
 - Certified Amount
 - The certified amount to previous period.
 - Payless Amount
 - The payless amount to the previous period.
							
Formula: Payless Amount = Applied Amount – Assessed Amount. - Remaining Amount
 - The remaining amount to the previous period.
							
Formula: Remaining Amount = Ordered Amount – Applied Amount Previous Periods. - Current Period
 - 
					
- Applied Progress %
 - The applied progress
									percentage of the line order.Note:
- This field is enabled only if Services Line Type is set to a value other than Rate Only and Not Applicable.
 - If the Self-Billing check box in the Subcontracting Procurement Order (tdpur6600m000) session is selected, this field is defaulted from Assessed Progress %.
 
 - Assessed Progress %
 - The assessed progress percentage of the line
										order.Note: This field is enabled only if Services Line Type is set to a value other than Rate Only and Not Applicable.
 - Applied Quantity
 - The applied quantity in the current period.Note:
- This value can be modified if:
- The Assessment Basis field is set to Cumulative.
 - The AFP status is set to Received, In Process or Assessed.
 
 - This field is enabled only if Services Line Type is set to a value other than Amount Only and Not Applicable.
 - This value is populated based on the specified Applied Progress percentage.
 - The quantity cannot be greater than the Subcontracting Procurement Order Line quantity.
 
 - This value can be modified if:
 - Assessed Quantity
 - The assessed quantity of the line order.Note:
- This value can be modified if:
- The Assessment Basis field is set to Cumulative.
 - The AFP status is set to Received, In Process or Assessed.
 
 - This field is enabled only if Services Line Type is set to a value other than Amount Only and Not Applicable.
 - This value is populated based on the specified Assessed Progress percentage.
 - The quantity cannot be zero.
 - The quantity cannot be greater than the SPO line quantity.
 
 - This value can be modified if:
 - Payless Quantity
 - The payless quantity to the current period. 
Formula: Payless Quantity = Applied quantity – Assessed quantity. - Remaining Quantity
 - The remaining quantity to the current period. 
Formula: Remaining Quantity = Ordered quantity – Applied Quantity Current Periods. - Applied Amount
 - The applied amount for the line order. 
Formula: Applied Amount=Ordered Amount – Applied Amount Current Periods.Note:- This field is enabled only if Line Type is set to a value other than Not Applicable.
 - If the Self-Billing check box is selected for the related Subcontracting Procurement Order the Assessed Amount of the order is defaulted in this field.
 - This value is populated based on the specified Applied Progress % percentage.
 - The amount is expressed in the services procurement order currency.
 - The Applied Amount cannot be zero.
 - The sum of all of the AFP-lines for this AFP cannot be greater than the AFP Applied Amount.
 - In case of Cumulative this field is always calculated (just as all of the This Period
												fields): 
Formula: Current Period Value = Cumulative Value - Previous Periods Value. - In case of Assessment Basis Periodic, amount + total applied amount of other AFP lines cannot be greater than AFP Applied Amount.
 
 - Assessed Amount
 - The amount for the assessed services.Note:
- This field is enabled only if Line Type is set to a value Amount Only .
 - This value is populated based on the specified Assessed Progress % percentage.
 - The Assessed Amount is expressed in SPO currency.
 - The amount cannot be less than zero.
 
 - Payless Amount
 - The payless amount to the current period. 
Formula: Payless Amount = Applied amount – Assessed amount. - Remaining Amount
 - The remaining amount to the current period. 
Formula: Remaining Amount = Ordered Amount – Applied Amount Current Periods. 
 - Cumulative
 - 
					
- Applied Progress %
 - The cumulative applied progress percentage of the line order.Note:
- This value can be modified if:
- The Assessment Basis field is set to Cumulative.
 - The AFP status is set to Awaiting and the current date is equal to or later than the Assessment As At Date.
 - The AFP status is Initiated.
 
 - This field is enabled only if Line Type is set to a value other than Rate Only and Not Applicable.
 - If the Self-Billing check box is selected for the related Subcontracting Procurement Order the Assessed Progress of the order is defaulted in this field.
 
 - This value can be modified if:
 - Assessed Progress %
 - The cumulative assessed progress percentage of the line order.Note:
- This value can be modified if:
- The Assessment Basis field is set to Cumulative.
 - The AFP status is set to Received, In Process or Assessed.
 
 - This field is enabled only if Line Type is set to a value other than Rate Only and Not Applicable.
 
 - This value can be modified if:
 - Applied Quantity
 - The cumulative applied quantity of the line order.Note:
- This value can be modified if:
- The Assessment Basis field is set to Cumulative.
 - The AFP status is set to Awaiting and the current date is equal to or later than the Assessment as at Date.
 - The AFP status is Initiated.
 
 - This field is enabled only if Line Type is set to a value other than Rate Only and Not Applicable.
 - This value is populated based on the specified applied progress percentage.
 - The quantity cannot be greater than the Subcontracting Procurement Order Line quantity.
 
 - This value can be modified if:
 - Assessed Quantity
 - The assessed quantity of the line order.Note:
- This value can be modified if:
- The Assessment Basis field is set to Cumulative.
 - The AFP status is set to Received, In Process or Assessed.
 
 - This field is enabled only if Line Type is set to a value other than Amount Only and Not Applicable.
 - This value is populated based on the specified Assessed Progress percentage.
 - The quantity cannot be zero.
 - The quantity cannot be greater than the SPO line quantity.
 
 - This value can be modified if:
 - Payless Quantity
 - The balance quantity after deducting assessed quantity from the applied
									quantity. 
Formula: Payless Quantity = Applied Quantity – Assessed Quantity.Note: You cannot modify this value. - Remaining Quantity
 - The remaining quantity to the current period. Note: This value is calculated based on this
formula: SPO line value - Cumulative Assessed Value. You cannot modify this value.Formula: Remaining Quantity = Ordered quantity – Applied Quantity Current Periods. - Applied Amount
 - The amount applied for the line order. 
Formula: Applied Amount = Ordered Amount – Applied Amount Current Periods.Note:- This value can be modified if:
- The Assessment Basis field is set to Cumulative.
 - The AFP status is set to Awaiting and the current date is equal to or later than the Assessment As At Date.
 - The AFP status is Initiated.
 
 - This field is enabled only if Line Type is set to a value other than Amount Only and Not Applicable.
 - This value is populated based on the specified Applied Progress percentage.
 - This field is enabled only if Services Line Type is set to a value other than Not Applicable.
 - If the Self-Billing check box is selected for the related Subcontracting Procurement Order the assessed amount of the order is defaulted in this field.
 - The amount cannot be zero.
 
 - This value can be modified if:
 - Assessed Amount
 - The amount for the assessed services.Note:
- This value can be modified if:
- The Assessment Basis field is set to Cumulative.
 - The AFP status is set to Received, In Process or Assessed.
 
 - This field is enabled only if Line Type is set to a value Amount Only .
 - This field is defaulted if the Assessed Progress % is specified. is specified.
 - This amount is expressed in the currency specified for the related Subcontracting Procurement Order.
 - The amount must be greater than zero..
 
 - This value can be modified if:
 - Payless Amount
 - The payless amount for the current period. 
Formula: Payless Amount = Applied amount – Assessed amount.Note: You cannot modify this value. - Remaining Amount
 - The remaining amount for the current period. 
Formula: Remaining Amount = Ordered Amount – Applied Amount for Current Periods.Note: This value is calculated based on thisformula: SPO line value - Cumulative Assessed Value. You cannot modify this value. 
 - Miscellaneous
 - 
					
- Payless Text
 - Indicates if the payless text exists. The
									application selects this check box if the assessment amount is
									less than the applied amount.Note: This field is only applicable if line assessed is less than the line applied amount.