All Failed Tasks (pdwfl1522m400)
Use this session to view and maintain the failed tasks.
Field Information
- Priority
 -  
            
The priority set for the business process.
Allowed values
- Medium
 - Urgent
 - Low
 
 - Business Process Type
 -  
            
The type of business process.
Allowed values
- ECN
 - ECO
 - ECP
 - Approval Process
 - ECR
 
 - Business Process
 - The code of the business process.
 - Step/Task
 - The operation defined for the workflow. The assigned user must complete the operation (task) before the workflow can continue with the next step or task.
 - Arrival Date
 - The date on which the task is assigned.
 - PLM Project
 - The PLM project for which the item is created.
 - Workflow Template
 - The workflow template used for the workflow attached to the business process.
 - Current Step
 -  
            
Indicates that the step is the latest.
 - Status
 -  
            
The status of the task.
Allowed values
- Created
 - 
               
The Business Process is created.
 - In Progress
 - 
               
The Business Process is launched.
 - Completed
 - 
               
The Business Process steps are completed.
 - Rejected
 - 
               
The Business Process is rejected.
 - Suspended
 - 
               
The Business Process is temporarily kept on hold for a reason.
 - Failed
 - 
               
The system steps (Check-In, Check-Out) related to the Business Process have failed.
 - Fully Rejected
 - 
               
The Business Process is cancelled.
 
 - Exit Date
 - The date on which task is completed.
 - Reject To
 - The name of the user to whom the business process is assigned after rejection.