Order Planning Statistics (cprrp8100m000)
Use this session to view statistics per order planning run.
Field Information
- Run number
 - 
            
The identification number of the planning run.
 - Scenario
 - Session
 - 
            
The session from which Enterprise Planning retrieves the order planning.
 - User
 - 
            
The name of the user responsible for planning.
 - Job
 - 
            
The job ID.
 - Job sequence number
 - 
            
The sequence number of the planned item.
 - Number of Items
 - 
            
The total number of items planned.
 - Start Date
 - 
            
The start date of the run.
 - End Date
 - 
            
The end date of the run.
 - Run Time (hh:mm:ss)
 - 
            
The time it took for the planning run to be completed in hours, minutes and seconds.
 - Average Rate (items/sec)
 - 
            
The average planning rate in items per second for the selected run.
 - Number of parallel bshells
 - 
            
The number of servers (bshells) that calculate and actualize planning data.
Note: Number is always zero (0) if parallel processing is not active. - Stopped
 - 
            
If this check box is selected, the planning run was aborted before completion.
 - Loop detected
 - 
            
If this check box is selected, a loop was detected in the bill of material (BOM) structure of the item being planned.
 - Failure Messages
 - 
            
The number of failure messages generated during the planning run.