按外部发票成本行列出的项目成本 (tfacp7111m000)

使用此进程以查看和维护与外部(已收到)发票关联的成本行的项目成本。
注意

仅当在 ACP 参数 (tfacp0100m000) 进程中为外部采购发票定义编号组系列时,才能访问此进程。

您的概念

已收到的采购发票

The number of the received purchase invoice for which the project costs data must be maintained.

Note: 

This value is generated using the values defined in the 编号组 and 系列 of the 应付帐款参数 (tfacp0100m000) session.

行号

The position number of the external purchase invoice line.

序号

The sequence number of the cost line associated with the external invoice.

项目代码

The code of the project for which the costs must be calculated.

要素

The code of the element associated with the project.

成本类型

The cost type linked to the project.

允许值

人工
间接费用
合同发票
销售订单
服务维修
材料
设备
分包
杂项成本
收益
期中结果
在制品余量
成本对象

The cost object linked to the project.

计划

The code that uniquely identifies the plan to which the activity is linked.

活动

The code of the activity that is linked to the project.

延伸合同

The code that identifies the extension linked to the transaction of the cost line.

成本构成

The code of the cost component associated with the cost object.

数量

The quantity of the items expressed in the inventory unit.

单位

The code of the unit in which the quantity of the items is expressed.

时间量

The number of time units. For instance, the numbers of days that a crane has been employed for a project.

Total quantity of transaction = Amount of time x Quantity (rounded to two decimals).

时间单位

The code of the unit in which the amount of time is expressed.

员工

The code of the employee who creates the project costs for the external invoice.

工作类型

The code of the labor type applicable for the project.