Activity Workbench grid

In the grid of the Activity Workbench (tppss2600m000) , you can view the data based on the values specified in the Selection section and the filter options selected in the header.

This information is displayed:

  • The Days Left to Start column displays the number of days remaining for an activity to start. This is calculated from the current date to the scheduled start date of the activity, if the Actual Start Date is not specified for the activity. A negative number indicates that the activity must have started but has not yet started.
  • The Days Left to Finish column displays the number of days remaining to finish the activity. This is based on the actual start and finish dates specified for the activity.
  • The Percentage Complete column displays the progress of the activity. The values in this column are defaulted from the Schedule Percentage Complete field in the Activities (tppss2100m000) session.

See also, Activities (tppss2100m000) session