Maintaining a Budget Cost Analysis

  1. Create a new budget cost analysis version for the selected project using the Budget Cost Analysis Version (tpptc3100s000) session.
  2. Generate the analysis data, and specify the budget cost analysis version for which the analysis data is generated, using the Generate Budget Cost Analysis (tpptc3200m000) session.