Budgeted Equipment Costs (tpptc3547m000)

Use this session to display the budgeted amounts and quantities of the cost-type, equipment, for:

  • The selected project code
  • The budget-cost analysis code

Field Information

Project

The code that uniquely identifies the project.

Project Status

The project's status.

Budget Cost Analysis Version

The code that uniquely identifies the cost analysis.

Last Calculation Time

The date on which the latest budget-cost analysis was performed via the Generate Budget Cost Analysis (tpptc3200m000) session for the selected budget-cost analysis code.

Currency

The default currency in the overview session is the project currency. Both in a dependent and in an independent currency system you can change this currency to other currencies with the Rotate Currency option <CTRL-R>.

The following sequence is applicable:

  1. Project currency
  2. Local currency
  3. Reporting currency 1
  4. Reporting currency 2
Note: Only the last three currencies are home currencies.
Equipment

The code that uniquely identifies the equipment.

Reference Type

The nature of the equipment cost object.

Allowed values

Project

Specific to the selected project.

Standard

Common to all projects.

Amount of Time

The length of time the equipment is used.

Time Unit

The code that uniquely identifies the time unit.

Amount

The total cost of the budget line.