Update Assignments in Hours Accounting (tpptc2211m000)

Use this session to update assignments for a range of employees. The resource assignment is updated in the Assignments (bpmdm0130m000) session based on the employee assigned in the budget line.
Note: 
  • The Update process checks whether the start date in the Relative Details group box on the budget lines falls into the relative date range. If this field is empty LN checks the activity start date.
  • If the end date of a budget labor line is not filled, LN creates an infinite assignment from the budget line.
  • The Assignments (tpptc2170m000) session is not used.

Field Information

Project

The From and To fields define a range of: project.

Project Selection

The From and To fields define a range of: project.

Employee

The From and To fields define a range of: employees

Employee

The From and To fields define a range of: employees.

Related Start Date

The Update process considers the first related start date of the project. The activity start date must be in this range.

Budget Line Status

The status of the budget line.

Allowed values

Free

You can modify all the data.

Actual

You can modify the budget data and generate the control data. You can also log the budget history.

Final

You cannot modify the budget data. You can only add or modify the budget lines using a budget adjustment. You can also log the actual budget history.

Activity

The From and To fields define a range of: activities.

Error Report

If this check box is selected, LN generates an error report, if any.