Delete Budget (tpptc2203m000)
Use this session to delete the bottom-up budget lines for a range of elements or activities of a project. You can only delete the budget lines based on the status of the project , budget status, and budget adjustments. The report includes the deleted budget lines and the lines that are not deleted, and the reason for the deletion.
Example
- Generate Budget Cost Analysis (tpptc3200m000)
- Generate Control Data (tpptc1230m000)
Field Information
- Selection Range
-
- Selection Range
-
Use the fields in the Selection Range to specify the range of data for which you want to delete the budget lines.
- Structure Range
-
- Elements
-
If this check box is selected, the From and To fields related to the elements are enabled.
- From
-
The From and To fields define a range of: elements for which you want to delete the budget lines.
- Activities
-
If this check box is selected, the From and To fields related to the activities are enabled.
- From
-
The From and To fields define a range of: activities for which you want to delete the budget lines.
- Reports
-
- Process Report
-
If this check box is selected, LN prints the process report for the selected range of data.
- Error Report
-
If this check box is selected, LN prints the error report for the selected range of data.
- Cost Object
-
- Cost Object Selection
-
- Item
-
If this check box is selected, the From and To fields related to the item are enabled.
- From
-
The From and To fields define a range of: items for which you want to delete the budget lines for the specified elements or activities.
- Labor
-
If this check box is selected, the From and To fields related to the labor are enabled.
- From
-
The From and To fields define a range of: labor lines for which you want to delete the budget lines for the specified elements or activities.
- Equipment
-
If this check box is selected, the From and To fields related to the equipment are enabled.
- From
-
The From and To fields define a range of: equipments for which you want to delete the budget lines for the specified elements or activities.
- Subcontracting
-
If this check box is selected, the From and To fields related to the subcontracting are enabled.
- From
-
The From and To fields define a range of: subcontracting lines for which you want to delete the budget lines for the specified elements or activities.
- Sundry Cost
-
If this check box is selected, the From and To fields sundry cost are enabled.
- From
-
The From and To fields define a range of: sundry-cost lines for which you want to delete the budget lines for the specified elements or activities.