Element Budget (Equipment) (tpptc1512m000)
Use this session to list budget lines with an equipment cost-type for the selected element and project.
Field Information
- Project
-
The code that uniquely identifies the project.
- Description
-
The description or name of the code.
- Project Status
-
The project status.
- Element
-
The code that uniquely identifies the element.
- Description
-
The description or name of the code.
- Budget Status
-
The budget status of the element.
- Budget Date
-
The budget date that is used as the reference for currency transactions. By default, the budget date as specified for the project is added to the new budget lines.
- Buy-from Business Partner
-
The buy-from business partner.
- Budget Adjustment Code
-
The name of the adjustment.
- Adjustment
-
An asterisk indicates that the budget line belongs to an adjustment.
- Line
-
The code that uniquely identifies the line number.
- Equipment
-
The code that uniquely identifies the equipment.
- Description
-
The name of the adjustment.
- Amount of Time
-
The amount of time the equipment is used
- Time Unit
-
The code that uniquely identifies the unit.
- Cost Component
-
The cost component.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Budget Status
-
The budget-line status.
- Difference
-
The difference between the original, unadjusted budget and the adjusted budget.
- Currency
-
The currency.
- Contingency Amount
-
The provisional amount that includes the possible unexpected costs.