Rescheduling Messages for Subcontracting (tppss6507m000)

Use this session to view the rescheduling messages for subcontracting purchase orders that were generated during the last PRP run. You can view more details of a rescheduling message in the Rescheduling Messages for Subcontracting (tppss6107s000) details session.

Rescheduling messages are generated for PRP orders of the following types:

  • Firm-planned
  • Confirmed
  • Transferred

Rescheduling messages are not generated for transferred purchase budget lines.

Note: If you have acted on the rescheduling message, you can delete it in this session.

Field Information

Project

The code that uniquely identifies the project.

Description

The description or name of the code.

Project Status

The project status.

Sequence Number

The sequence number which identifies the rescheduling message.

Transaction Type

The origin of this particular transaction. The transaction origin (TROR) is the object that drives the transaction.

Following are the transaction origins:

  • Purchase Order for transferred PRP purchase orders
  • Purchase Schedule for transferred PRP purchase orders
  • PRP Purchase Order for the Firm-planned or Approved status
  • Request for Quotation for transferred PRP purchase orders
Order Number

The code of the order to which this message applies.

Position Number

The position number of the order line. As an order can have multiple order lines, this number is used to identify the particular line to which the rescheduling message applies.

Sequence Number

The sequence number of the order line detail.

Subcontracting

The code that uniquely identifies the subcontracting item.

Description

The description or name of the code.

Reference Type

Indicates that subcontracting must be standard or project specific.

Rescheduling Message

The type of rescheduling message.

Allowed values

Reschedule In

The order must be delivered earlier. There is a discrepancy between the delivery date on the order and the required delivery date. This can be caused by:

  • The start date of the element (or, if not available, the project) being moved up.
  • The start date of the activity budget line being moved up (either manually or as a result of changes in the external scheduling package).
  • The delivery date of the order being deliberately postponed.
Reschedule Out

The order must be delivered later. There is a discrepancy between the delivery date on the order and the required delivery date. This can be caused by:

  • The start date of the element (or if not available, the project) being postponed.
  • The start date of the activity budget line being postponed (either manually or as a result of changes in the external scheduling package)
  • The delivery date of the order being deliberately moved up.
Cancel

There is a discrepancy between the quantity on the order and the required quantity. (Part of) the quantity is no longer required.