Planned PRP Purchase Order (Equipment) (tppss6111m000)

Use this session to maintain planned purchase orders related to external equipment.

Note: 

Initially, the planned order date and the planned delivery date are set based on the control budget and the lead time. The planned delivery time is determined in this way:

  • If the control budget is of type Activity, the planned delivery time generated from the activity budget line.
  • If the control budget is of type Element, the planned delivery time is generated from the element.
  • If the requirement is caused by an extension and the extension date is later, the extension date becomes the planned delivery time.
  • If no start date is found, the project planned delivery time is used.
  • If a generated planned order time occurs in the past, it is changed to the current date. This will also shift the planned delivery time.
Note: 

If the Authorization and Security functionality is implemented for Project, the usage of various fields such as project, warehouse, purchase contract, and enterprise unit are determined based on the specified permissions. See Authorization and Security

Field Information

Project

The code that uniquely identifies the project.

Status

The current project status. This status must be Free or Active, for all PRP orders in this session.

Allowed values

Free
Active
Finished
Closed
Archived
Order

The code that uniquely identifies the planned PRP equipment purchase-order.

If you create a new order, this field displays the chosen order series. If you save the PRP order, the first free number of the series is automatically allocated.

Planned Order
Equipment Order
Equipment

The equipment code.

Reference Type

The planned PRP purchase order's reference type.

Allowed values

Project

Specific to the selected project.

Standard

Common to all projects.

Amount of Time

The number of time units for which the equipment is ordered.

Unit of Measure

The unit of measure in which the amount of time is expressed.

Ship-to Address

The ship-to code and description.

Note: This value is defaulted based on the address that is defined for the activity. If the address is not defined for the activity, the project address is defaulted.
Order Status

The current order's status. This shows the extent to which the order has been processed.

Allowed values

Planned

The order can be either inserted manually or generated automatically. It will be replaced by the next generation run.

Firm-Planned

The order cannot be changed or deleted by a subsequent generation run. It can however be manually changed.

Approved

The order is protected from manual changes and also from the next generation run. Additionally, it can be transferred.

Transferred

The planned purchase order can be handed over to a purchase order in Procurement .

Canceled

The order is set to be deleted in the next generation run. (If the run is executed, this order is deleted unless you revise your decision).

Order Text

If this check box is selected, a text is present.

Business Partners
Request for Quotation

If this check box is selected, LN creates a request-for-quotation (RFQ) instead of a purchase order.

Note: This check box is visible, only if the Requests for Quotation option is selected in the Procurement Parameters (tdpur0100m000) sessions.
Buy-from Business Partner

The code that uniquely identifies the buy-from business partner.

If this field is clear, and you transfer the PRP purchase order, LN creates a request for quotation (instead of a purchase order).

Note: When you modify the data in this field, the application displays a message to confirm the retrieval of the Purchase Rate and Discount from the selected business partner.
Buy-from BP Description

The business partner's name.

Ship-from Business Partner

The code that uniquely identifies the ship-from-business-partner.

Cost Control
Element

The element to which the cost object of this order belongs.

Activity

The activity to which the cost object of this order belongs.

Extension

The contract extension to which the cost object of this order belongs.

Cost Component

The cost component of the cost object of this order.

Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.
Dates
Planned Order Date

The planned date and time to order the purchase.

Click Calculate, if you want to reset order date.

Start Time

The first day of the period for which you need the equipment.

Click Calculate, calculate the delivery time from the planned order time plus the lead time.

Finish Time

The last day of the period for which you need the equipment.

Transaction Time

The transaction date and time for the planned purchase order.

Planning
Buyer

The code that uniquely identifies the buyer.

Note: 
  • LN defaults the value when the planned PRP orders are generated, using the Generate Planned PRP Orders (tppss6200m000) session.
  • When you specify a value in this field, Infor LN checks if the specified employee’s data exists in the Employees - People (bpmdm0101m000) session and the employee is Active (based on the First Date of Employment and the Last Date of Employment). Else, a warning message is displayed. You can ignore the message.
Name

The name of the buyer.

Planner

The planner.

Note: 
  • The value of this field is defaulted from the Planner field, in the Project Equipment (tppdm6512m000) or Equipment (tppdm0512m000) session.
  • When transferring a Planned PRP Purchase Order (Equipment), this data is transferred to the Purchase Order line and to the Order Line Balance (Equipment) (tppss6501m000).
  • When you specify a value in this field, Infor LN checks if the specified employee’s data exists in the Employees - People (bpmdm0101m000) session and the employee is Active (based on the First Date of Employment and the Last Date of Employment). Else, a warning message is displayed. You can ignore the message.
Purchase
Purchase
Purchase Office

The purchase office that purchases equipment according to transferred PRP purchase orders.

Purchase Type

The default purchase type. You can change the value or leave this field empty.

Pricing
Purchase Contract

The purchase contract (defined in Procurement ) according to which the item is purchased.

Note: This field is visible, only if the Contracts option is selected in the Procurement Parameters (tdpur0100m000) session.
Contract Line

The position number of the purchase contract to which the planned purchase order is related.

Note: This field is visible, only if the Contracts option is selected in the Procurement Parameters (tdpur0100m000) sessions.
Purchase Rate

The currency of the purchase price of the planned purchase order.

Purchase Rate

The price per time unit at which you purchase the selected equipment. Click the Calculate Lease Rate button to calculate the price rate of the planned purchase order for equipment.

The price rate is determined by the information in the Pricing module under Common . If the currency matches, you can retrieve prices from the price matrices. If these are no prices available in the matrices LN looks at the contracts and then at the price of the cost object.

Final Unit Cost

If this check box is selected, the purchase price is considered as the final price. However, if you modify the Purchase Rate, the Price Origin is set to Manual.

Price Origin

The origin of the price specified for the planned purchase order.

Allowed values

Item Purchase Data

The sales price originates from the Item - Purchase session.

Item Sales Data

The sales price originates from the Items - Sales (tdisa0501m000) session.

Item Service Data

The sales price originates from the Items - Service (tsmdm2100m000) session.

Supplier Price Book

Default Price Book

The sales price originates from the default sales price book entered in the Price Books (tdpcg0111m000) field of the Pricing Parameters (tdpcg0100m000) session.

Price Structure

The sales price originates from a price book linked to the Pricing Control (PCG) matrix of the price matrix type.

Not Applicable
External

The price originates from an external package.

Generic Price List
Manual

The sales price is entered manually.

Contract

The sales price originates from a sales contract.

Product Variant

The price originates from the Product Configuration module.

Price from Derived Equipment

If this check box is selected, the price is retrieved from the standard equipment cost object.

Discount

The discount percentage that is applicable for the planned purchase order.

Note: When you add or modify the data in this field, by default, the Discount Origin field is set to Manual.
Discount Origin

The origin of the discount, as specified for the business partner on the planned purchase order.

Allowed values

Contract

The discount originates from a purchase contract.

Discount Structure

The discount originates from a Pricing Control (PCG) matrix of the type discount matrix. For more information, refer to Setting up a discount matrix.

Price Book Discount Structure

The discount originates from the price book to which a discount schedule is linked.

Project Equipment

The discount origin is based on the data specified in the project equipment.

Standard Equipment

The discount origin is based on the data specified in the standard equipment.

Project Subcontracting

The discount origin is based on the data specified in the project subcontracting.

Standard Subcontracting

The discount origin is based on the data specified in the standard subcontracting.

External

The discount originates from an external package.

Manual

The discount is manually entered.

Not Applicable

The discount is not applicable.

Note: This field is set to Manual, when you add or modify the data in the Discount field.
Amount

The total price of the planned purchase order.

Additional Information
Additional Field

User-defined fields that can be linked to LN tables. Additional information fields do not add any specific value to LN as functional logic is not linked to the contents of these fields.

Note: When creating or generating the Planned PRP purchase order, LN defaults the additional information fields from the Contract Line, that is linked to the project peg of the planned order.

Text
Text

The additional information related to the item as part of the planned order.

Image

The image of the item as defined in the equipment master data.