Performance Measurement Using EVM Graph (For Home Page) (tppss0801m000)

Use this session to create a graph of the performance figures in the Performance Measurement Activity (tpppc5540m000) session. The graph provides an insight into the totals per project. You can adjust your planning based on the Schedule Variance and the Cost Variance.

Note: You can start this session from the Project Manager Homepage. The Project Manager Homepage can be viewed only from the LN UI.

Field Information

Project

The code of the project.

Project

The description or name of the code.

Periods

The first year for which you want to display the graph.

/

The first period for which you want to display the graph.

/

The last year for which you want to display the graph.

/

The last period for which you want to display the graph.

Generate Code

The code of the generated performance measurement that you want to display.

Currency

currency.

Description

The description or name of the code.

Planned Value

If this check box is selected, the budgeted costs of work scheduled are displayed.

Earned Value

If this check box is selected, the budgeted costs of work performed are displayed.

Budget at Completion

If this check box is selected, the Budget at Completion (BAC) is displayed.

Estimate at Completion

If this check box is selected, the Estimate at Completion (EAC) is displayed.

Note: The EAC can not be displayed if the leading forecast method is Estimate Extra Cost.
Actual Cost

If this check box is selected, the actual costs are displayed.

Include Commitments

If this check box is selected, the commitments are included in the actual costs.

Actual Revenues

If this check box is selected, the actual revenues are displayed.

Note: Actual Revenues are registered when project data is transferred in the Transfer Transactions to Invoicing (tppin4200m000) session.
Planned Revenues

If this check box is selected, the planned revenues are displayed.

Note: Planned revenues are obtained from advances and installments.
Include Forecast

If this check box is selected, the forecasts are included in the planned revenues.

Material Costs

If this check box is selected, the material costs are displayed.

Subcontracting Costs

If this check box is selected, the subcontracting costs are displayed.

Labor Costs

If this check box is selected, the labor costs are displayed.

Sundry Cost

If this check box is selected, the sundry cost are displayed.

Equipment Costs

If this check box is selected, the equipment costs are displayed.