Activity Workbench (tppss2600m000)
Use session to view and filter the activities. The activities can be filterd based on the
Work Authorization Status, Due Date, Incomplete Labor Lines, and so on. This helps in
identifying the activities that require immediate attention.
Note:
For more information, see:
- Activities (tppss2100m000)
Field Information
- Selection
-
- Project Manager
-
The name of the project manager.
- Activity Manager
-
The name of the activity manager.
- Project
-
The code of the project.
- Project Location
-
The location of the project.
- Period
-
- Date From
-
The date and time from when the activities are displayed.
- Date to
-
The date and time up to which the activities are displayed.
- Due Date
-
The due date based on which the activities are filtered.
Allowed values
- Scheduled Start Date
- Scheduled Finish Date
- Earliest Start Date
- Latest Start Date
- Earliest Finish Date
- Latest Finish Date
- Constraint Date
- Work Authorization Status
-
- On Hold
-
Click
to activate this filter. The number of activities within the selection that are on hold, are displayed. Infor LN selects the corresponding check box when you apply this filter. - Free
-
Click
to activate this filter. The number of activities within the selection that are free, are displayed. Infor LN selects the corresponding check box when you apply this filter. - Released
-
Click
to activate this filter. The number of activities within the selection that are released, are displayed. Infor LN selects the corresponding check box when you apply this filter. - Finished
-
Click
to activate this filer. The number of activities within the selection that are finished, are displayed. Infor LN selects the corresponding check box when you apply this filter. - Closed
-
Click
to activate this filer. The number of activities within the selection that are released, are displayed. Infor LN selects the corresponding check box when you apply this filter.
- Due Date
-
- Past Due
-
Click
to activate this filter. The activities for which the scheduled start date is before the current date, are displayed. Infor LN selects the corresponding check box when you apply this filter. - Today
-
Click
to activate this filter. Activities for which the scheduled start date is the current date, are displayed. Infor LN selects the corresponding check box when you apply this filter. - 1 - 7 days
-
Click
to activate this filter. Activities for which the scheduled start date is within 1 to 7 days from the current date, are displayed. Infor LN selects the corresponding check box when you apply this filter. - Beyond 7 days
-
Click
to activate this filter. Activities for which the scheduled start date is 8 or more days from the current date, are displayed. Infor LN selects the corresponding check box when you apply this filter. - No Date
-
Click
to activate this filter. Activities for which date is not specified, are displayed. Infor LN selects the corresponding check box when you apply this filter.
- Incomplete Labor Lines
-
- Allocated Hours
-
Click
to activate this filter. Activities for which hours are allocated, are displayed. Infor LN selects the corresponding check box when you apply this filter. - Assignments
-
Click
to activate this filter. Assignments with the status Free, are displayed. Infor LN selects the corresponding check box when you apply this filter.
- Not Approved
-
- PRP Purchase Orders
-
Click
to activate this filter. Activities for which the linked PPR purchase orders are required to be approved, are displayed. Infor LN selects the corresponding check box when you apply this filter. - PRP Warehouse Orders
-
Click
to activate this filter. Activities for which the PPR warehouse orders are required to be approved, are displayed. Infor LN selects the corresponding check box when you apply this filter.
- Graph
-
The graphical representation of the data displayed in the grid. This data is displayed as a mix of a stacked and a standard bar graph.
Note: You can select Costs or Hours to view the data in the graph. The data in the graph is displayed based on the period specified in the Project Accounting Parameters (tpppc0100s000) session.