Cost Surcharges by Project (tpppc2580m000)

Use this session to list cost surcharges for a combination of the project and the surcharge code.

Field Information

Project

The code that identifies the project.

Project Status

The project status.

Sundry Cost

The sundry-cost code's code to which the surcharge is posted.

Sequence Number

The sequence number code.Uniquely identifies the surcharge.

Percentage

The surcharge percentage.

Element

The element code to which the calculated surcharge must be posted. If you leave this field blank, the surcharge is posted to the element under which the cost, on which the surcharge is calculated, has been recorded.

Cost Component

The cost component code to which the surcharge is posted. If you leave this field blank, the surcharge is posted to the cost component that contains the costs on which the surcharge is calculated.

Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.