Material Cost Forecast (tpppc2116m000)

Use this session to maintain material cost forecasts for the project. These values are used to compute forecast amounts in control enquiries and report sessions.

Field Information

Project

The code of the project.

Description

The description or name of the code.

Project Status

The status of the project.

Allowed values

Free
Active
Finished
Closed
Archived
Registration Date

The date when the material cost forecast is registered.

Cost Object
Element

The code of the element.

Description

The description or name of the code.

Work Authorization Status

The work authorization status of the element.

Activity

The code of the activity.

Description

The description or name of the code.

Work Authorization Status

The work authorization status of the activity.

Item

The code of the item.

Note: 

You can select the code from one of these sessions:

  • Items - Project (tppdm0505m000) session.
  • Control Data (Material Lines) (tpptc1535m000) session.
Description

The description or name of the code.

Cost Component

The code of the cost component.

Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.
Description

The description or name of the code.

Currency

The currency specified for the cost object.

Note: This field is disabled if the Final Rate checkbox is selected.
Unit Cost

The standard cost of the item per unit.

Note: 
  • This field is enabled only if you specify the value in the Forecast Quantity field.
  • This field is disabled if the Final Rate checkbox is selected.
Final Rate

If this check box is selected, the Unit Cost is considered as the final cost rate.

Note: 
  • If the forecast amount is modified with the Final Rate checkbox cleared, Infor LN recalculates the Unit Cost.
  • If the forecast amount is modified with the Final Rate checkbox selected, Infor LN recalculates the forecast quantity.
Currency Rate/Rate Factor

The currency rate.

Rate Factor

The rate factor.

Text

Indicates if text is present.

Cost
Budget

The total amount of the material that is budgeted for the element or the activity.

Budget Quantity

The total quantity of the material that is budgeted for the element or the activity.

Earned Value

The earned value.

Physical Progress

The physical progress percentage.

Actual

The actual cost of the material cost.

Quantity

The actual quantity of the material specified on the cost line.

Forecast
Forecast Quantity

The forecasted material quantity.

Unit

The unit in which the forecast material quantity is expressed.

Cost Amount

The total forecasted cost amount for the material.

Cost Amount (Home Currency)

The total forecasted cost amount for the material that is expressed in home currency.

Note: This value is defaulted from the Unit Cost field.
Home Currency

The home currency code.

Estimated Extra Costs

The additional amount over the estimated budget amount.

Note: This field is visible only if the Leading Forecast Method field is set to Estimated Extra Costs, in the Project Accounting Parameters (tpppc0100s000) session.
Estimate to Complete

The estimated cost to complete the activity.

Note: This field is visible only if the Leading Forecast Method field is set to Estimate to Complete, in the Project Accounting Parameters (tpppc0100s000) session.
Estimate at Completion

The estimated cost at the project completion.

Note: This field is visible only if the Leading Forecast Method field is set to Estimate at Completion, in the Project Accounting Parameters (tpppc0100s000) session.
Approved

If this check box is selected, the forecasted material cost is approved. Only the approved cost forecast reports are considered for cost control and interim results.

Note: After the forecasted amount is approved, you cannot modify the forecast data.
Variance
Variance

The actual cost variance of the material cost.

Forecast Variance

The forecasted cost variance of the material cost.