Generate Physical Progress by Extension/Cost Object (tpppc1188m000)

Use this session to update the progress of extensions at the extension level or at the cost object level (determined from the progress registration level).

Field Information

Project

The code that identifies the project.

Description

The description or name of the code.

Project Status

The project status.

Physical Progress Date

The date for which progress will be generated.

Material

If this check box is selected, progress data is generated for the item cost object.

Material

The progress percentage of the item cost object.

Labor

If this check box is selected, progress is generated for the labor cost object.

Labor

The progress percentage of the labor cost object.

Equipment

If this check box is selected, progress is generated for the equipment cost object.

Equipment

The progress percentage of the equipment cost object.

Subcontracting

If this check box is selected, progress is generated for the subcontracting cost object.

Subcontracting

The progress percentage of the subcontracting cost object.

Sundry Cost

If this check box is selected, progress is generated for the sundry cost cost object.

Sundry Cost

The progress percentage of the sundry cost cost oject.

Reported Completed

If this check box is selected, master lines are generated independently from the value of the Register Progress field for the project or the cost object.

Delete Existing Data

If this check box is selected, the progress that is newly generated for existing lines replaces the old generated control data progress of these lines. What remains is the new progress.

If this check box is cleared, LN will leave the lines that were deleted after generating control data in tact in the history when you generate new progress here. For lines that new progress is generated for, the old lines will be updated.

Record Physical Progress

Use this field to choose how to record stages.