Standard Surcharges by Cost Component (tppdm1571m000)

Use this session to list the standard surcharges by cost component. These surcharges are standard surcharges that are available to all projects. You can also define project-specific surcharges by using the Surcharges (tpppc2880m000) session and its derivatives. These cost surcharges are posted to Financials when costs and commitments are processed via the Process Transactions (tpppc4802m000) session. Each line in this list refers to a unique combination of company, cost component, sundry cost code, and sequence number. While each line can share characteristics with other lines in the list, its combination of characteristics is unique. For example, you could have a number of surcharges posted to the same sundry cost object code, as long as they differ in at least one other characteristic.

Note: You can define and modify standard surcharges by cost component in the Standard Surcharge by Cost Component (tppdm1171s000) session

Field Information

Company

The company that the surcharge applies to.

Cost Component

The cost component from which the surcharge is calculated.

Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.
Sundry Cost

The code that identifies the standard sundry cost object where the surcharge is posted.

Description

The description or name of the code.

Sequence Number

This number uniquely identifies the surcharge in combination with the other surcharge characteristics, such as cost component, sundry cost, and so on. This number is automatically assigned when you create a new surcharge. Surcharges can share a common sequence number, as long as they differ in at least one other characteristic.

Percentage

The surcharge percentage. The surcharge amount will vary depending on the budget, costs, and/or revenues (as specified in the Surcharge Type fields).

Estimate

If this check box is selected, Infor LN considers the surcharge when calculating the surcharges for the estimate for the project.

Budget

If this check box is selected, the surcharge is calculated on the budgeted costs in the actual budget. The surcharge is posted as sundry cost in control data. The surcharge type indicates how the surcharge is recorded. You can check any combination of surcharge types.

Costs

If this check box is selected, the surcharge is calculated based on actual costs and commitments. The surcharge is posted as sundry cost in cost registration. The surcharge type indicates how the surcharge is recorded. You can check any combination of surcharge types.

Revenues

If this check box is selected, the surcharge is calculated based on revenues. This only applies to cost objects of cost type General. The surcharge is posted as sundry cost in cost registration. The surcharge type indicates how the surcharge is recorded. You can check any combination of surcharge types.

Estimate Surcharge Method Cost

If this check box is selected, the estimate surcharge calculated using the Calculate Estimate Surcharges (tpest2200m100) session is added to the cost amount specified in the Estimate Lines (tpest2100m000) session.

Default value

By default, this check box is selected.

Note: This field is enabled only if the Estimate check box is selected.
Estimate Surcharge Method Sales

If this check box is selected, the estimate surcharge calculated using the Calculate Estimate Surcharges (tpest2200m100) session is added to the sales amount specified in the Estimate Lines (tpest2100m000) session.

Note: This field is enabled only if the Estimate check box is selected.