Renumber Estimate Lines (tpest2202m000)

Use this session to renumber the sequence of estimate line. The session renumbers the estimate lines only for an estimate version with the status Free. You can, for example, create a step size for more overview or to be able to enter lines in between the renumbered line numbers.

Field Information

Project

The code that identifies the project.

Description

The description or name of the code.

Status

The project status.

Version

The code that identifies the estimate version.

Description

The description or name of the code.

Status

The status of the estimate version.

Starting Line Number

Step Size

The sequence steps.

For example, the sequence number begins with 10, the step size is 10, which means that the next sequence numbers is 20, 30, and so on.

Sort By

If you renumber the estimate lines, you can use the sort structure to sort the estimate lines by an additional structure. As a result, the lines are organized with the additional structure's new sequence of codes.