Machine Utilization Workbench Header

The header section of the Machine Utilization (tisfc8365m000) workbench displays the Key Performance Indicators (KPIs) and the Predicted Order Completion chart for the selected week.

You can view this information in this section:

Key Performance Indicators (Week)
For the selected week, these KPIs are displayed:
  • Average Lateness: The lateness of an order is defined as the time difference between the due date and planned finish date. This time difference is calculated based on the site calendar and is expressed in days. The average lateness is the total number of late days divided by the number of orders.
  • Predicted Orders Completed in Time: The numbers of orders that are on time or early, divided by the total number of orders. This value is expressed in percentage.
  • Average Bottleneck Utilization: The sum of the utilizations of the machines divided by the number of machines. This value is expressed in percentage.
  • Number of Orders: The total number of the production orders with the status Created, Released, Finished or Interrupted, and within the selected dates.
  • Average Machine Utilization: The average utilization of all the machines in the selected Production Department. This value is expressed in percentage.
  • Number of Operations: The total number of machine operations linked to the production orders that are defined within the selected time frame
Predicted Order Completion
This is a graphical representation for the distribution of the early or late orders.