Rescheduling Production Orders

To reschedule a range of JSC production orders in the Replan Production Orders (tisfc3240m000) session by order or order group:

  1. Select By Group in the selection range.

  2. Select to which site the selection applies, if multisite functionality is activated.

  3. Select a range of JSC Order Groups in the Group Selection group box.

  4. Select the desired print options in the Processing Print Options group box.
  5. Click Replan. The Reschedule Production Orders (tisfc3140m000) session starts. This session displays a list of all JSC production orders falling within the selection range.
  6. Per production order, change the Modified Production Start Date and the Modified Requested Delivery Date.
  7. On the appropriate menu, click Process Production Orders.
  8. If you selected one or more print options, the Select Device (ttstpsplopen) session starts. Specify an output device for printing the reports.
  9. Click Continue. The selected orders are rescheduled and a report is printed.