Reprocessing Production Orders

You can only use this session for production orders whose status is:

  • Created
  • Scheduled
  • Printed

If the Regenerate for Net-Change JSC Items Only check box is selected, material requirements are recalculated for items with changes to their BOM or routing. In that case, the Net Change JSC check box in the Item - Production (tiipd0101m000) details session is selected. Only the orders and operations for those items are replanned. If all production orders of the item are reprocessed correctly, the Net Change JSC check box in the Item - Production (tiipd0101m000) details session is cleared.

When you run this session, the order status changes to Created. All the manual changes that you have made (for example, in the Production Planning (tisfc0110m000) session) are undone.

Note: If a production order distribution plan is present for a production order, this distribution (including the operation distribution and the material distribution) is deleted during reprocessing. The distribution is not created again.