Print Shared Work Center Utilization by Day (tisfc1406m000)

Use this session to print a report showing what capacity usage is planned for a range of secondary work centers. The capacity is shown for each primary work center, whose capacity is allocated to various secondary work centers.

Before you can use this session you must run the Build Utilization (tisfc0201m000) session. You must select Automatic or Manual in the Update Method Day Utilization field and Automatic or Manual in the Update Method Week Utilization field in the Production Order Parameters (tisfc0100s000) session to update the plans on a daily basis.

Field Information

Min Man Utilization

Define a minimun percentage for the man utilization that LN must use as a criterion to select the work centers for which it must print a report.

The value that you define, acts like a filter.

Min M/C Utilization

Define a minimun percentage for the man/capacity utilization that LN must use as a criterion to select the work centers for which it must print a report.

The value that you define, acts like a filter.

Previous Operation Must be Completed

If this check box is selected, the only operations printed are, either

  • Start operations,
  • Operations for which all previous operations have been completed.

The resulting report lists planned operations which can actually be started at the secondary work centers.

Sort

Select which report you want to print.

Allowed values

  • by Day
  • by Company by Day