Print Work Center Utilization by Day (tisfc1403m000)

Use this session to produce a report that shows how much you have planned to use a selection of work centers by day.

  • You can only use this session if you have selected Automatic or Manual in the Update Method Day Utilization field and Automatic or Manual in the Update Method Week Utilization field in the Production Order Parameters (tisfc0100s000) session.

  • You can display an overview of work center usage in the Work Center Utilization by Day (tisfc1506m000) session.
  • You can print a utilization report for shared work center with the Print Shared Work Center Utilization by Day (tisfc1406m000) session.
  • You can print a report that shows which operations you can start.

Field Information

Previous Operation Must be Completed

If this check box is selected, the only operations printed are:

  • Start operations,
  • Operations for which all previous operations have been completed.