Job Shop Bills of Material (tibom3100m000)
Use this session to manage bills of material (BOM) header data for multi-site BOMs used during production in the job shop.
Field Information
- Site
-
site
- Product
-
The product for which you want to manage the bill of material (BOM).
- Bill of Material
-
The bill of material number.
- Revision
-
The bill of material revision.
- Effective Date
- Status
-
The status of the production bill of material.
Allowed values
- New
- Approved
- Expired
- Bill of Material
-
- Routing
-
The sequence of operation required to manufacture an item.
Note: A bill of material may be linked to a specific routing. If this field is empty, the bill of material can be used with any routing. - Use for Planning
-
If this check box is selected, the selected JSBOM is used for planning.
Note: Per item and site, only one Job Shop bill of material can be used for planning. - BOM Quantity
-
BOM quantity
- Use for Costing
-
If this check box is selected, the selected JSBOM is used for costing.
Note: Only one JSBOM per product can be used for costing purposes.
- Revision
-
- Expiry Date
-
The date after which the PBOM is no longer valid.
- Created By
-
The name of the employee responsible for the creation of the PBOM.
- Created On
-
The date the PBOM was created.
- Approved By
-
The employee responsible for the approval of the production bill of material.
- Approved On
-
The date the production bill of material was approved.
- Expired By
-
The eployee responsible for expiring the production bill of material.
- Expired On
-
The date the production bill of material was expired.
- Text
-
If this check box is selected, a text is present.
- Source
-
The origine of the job shop bill of material.
Allowed values
- Manual
-
The P-BOM is defined in the Production Bills of Material (timfc3100m000) session.
- Production Bill of Material
-
The P-BOM revision was generated from an existing production bill of material.
- Engineering Bill of Material
-
The P-BOM is generated from an engineering bill of material.
Note: If the P-BOM is generated from an E-BOM, the Source Engineering Item and Source Revision fields are filled. - Configurator (PCF)
-
The P-BOM is generated from data imported from the PCF configurator.
- Configurator
-
The P-BOM is generated from data imported from Infor Configurator.
- PLM
-
The P-BOM is generated from data imported from PLM.
- Job Shop Bill of Material
-
The P-BOM was generated from a job shop bill of material.
- Not Specified
- Source Revision
-
If the bill of material is derived, this is the source of the bill of material revision.