Integration Relation to Infor LN People (tfcat2121s000)

Use this session to maintain the integration relations with People. These allocation relations are used in the Import Actual Performance (tfcat2220m000) session to import the actual hours from People.

Field Information

Dimension Type

The dimension type for which you view or maintain the integration relations.

Dimension

The dimension to which the hours will be imported when you start the Import Actual Performance (tfcat2220m000) session.

Reference Unit

The reference unit for which you want to import the actual hours.

Serial Number

The serial number of the current relation for this dimension/reference unit combination.

Logistic Company

The logistic company in which the hours are registered.

Allowed values

Select a logistic company that is linked to the current financial company. In addition, the first day of the week of the selected company must be the same as the first day of the week of the current company.

Default value

The default value is the current company.

Kind of Hours

The type of hours to which the integration relation applies.

Hours control object

The type of logistic origin of the hours.

The values that you can select depend on the value of the Kind of Hours field.

If the Kind of Hours field is Labor Time, you can select all the values.

If the Kind of Hours field is Machine Time, you can select:

  • Work Center.
  • Project (PCS).
  • Machine.
  • Manufacturing Task.
  • Production Order.

If the Kind of Hours field is Indirect Hours or Absence Hours, you can select:

  • Work Center.
  • Employee.
  • General Task.
  • Cost Component.
Work Center

The work center for which hours must be imported and allocated to the dimension of the integration relation.

You can enter a value only if the type of integration is one of the following:

  • Work center.
  • Employee hours/work center.
  • Machine hours.
Employee

The employee for which the actual hours must be imported and allocated to the dimension of the integration relation.

Name

The employee's name.

Machine

The machine for which the actual hours must be imported and allocated to the dimension of the integration relation.

Cost Component

The cost component for which the actual hours must be imported and allocated to the dimension of the integration relation.

Project

The project for which hours must be imported and allocated to the dimension of the integration relation.

General Task

The general task for which the hours must be imported.

Manufacturing Task

The Manufacturing task for which the hours must be imported.

Service Task

The Service task for which the hours must be imported.

Order from

If the Hours control object is an order type, you can enter a range of order numbers for which the data must be imported.

The Order from field and Order to field define the range of orders. To import the data for a single order, enter the same order number in both fields.

Order to

If the Hours control object is an order type, you can enter a range of order numbers for which the data must be imported.

The Order from field and Order to field define the range of orders. To import the data for a single order, enter the same order number in both fields.