Deleting Master Plan

To delete master plans:

  1. Specify a scenario and a plan level.
  2. Select a range of plan items, channels, and/or resources.
  3. Click Delete.

When an item master plan is deleted, LN also deletes all data that is directly linked to the item's production plan:

  • The critical material requirements
  • The component CTP reservations
  • The critical capacity requirements
  • The capacity CTP reservations
  • The capacity use that is recorded for the production plan

Moreover, if you select the Delete Planned Orders check box, LN deletes all planned orders for the item and the data that is directly linked to these orders:

  • The planned receipts and requirements recorded for each planned order in the Planned Order - Inventory Movements (cprrp0511m000) session.
  • The capacity use that is recorded for each planned production order.