Budget by Department (bptmm3110m000)

Use this session to enter budgeted hours, or to retrieve hours from the specified calendar.

Note: 

Budgeted costs are calculated using either of the following:

  • The applicable operation rate if a work center is used
  • The applicable labor rate if a service department is used.

Field Information

Department

The code of the department for which budgets are maintained.

Period Table Code

The period table code.

Year

The year in which the hours are booked.

Period

period code

Man Hours

The budgeted man hours.

Machine Hours

The budgeted machine hours.

Currency

currency

Labor Costs

The budgeted labor costs.

Machine Costs

The budgeted machine costs.

Overhead Costs

The budgeted overhead costs.