Data Upgrade Tasks (ttspt2520m100)
Use this session to display or maintain detailed information of a data upgrade task.
In the tabs of the session, these satellite sessions are displayed:
- Files (ttspt2530m000)
- Tables (ttspt2521m000)
- Pre-requisites (ttspt2522m000)
-
Sub-Tasks (ttspt2535m000)
Sub-tasks are defined in the upgrade programs delivered by Infor and are created during the initialization of a Data Upgrade Run.
Actions/Reference menu
This option is available:
-
Starts the Global Change Source Feature Pack (ttspt2220m000) session.
- Package Combination
-
The package combination for which the data upgrade run will perform an upgrade.
- Run Number
-
The run number of the data upgrade run.
- Company
-
The company for which the data upgrade run will perform an upgrade.
- Upgrade Program
-
The package code of the upgrade program.
- Upgrade Program
-
The module code of the upgrade program.
- Upgrade Program
-
The library code of the upgrade program.
- Source Feature Pack
-
The number of the source feature pack for which the upgrade program performs an upgrade.
The source feature pack defines the steps the upgrade program will perform.
Caution!
Note: You can also change the source feature pack in the Global Change Source Feature Pack (ttspt2220m000) session. You can start this session in the appropriate menu. - Runtime Class
-
The runtime class of the upgrade program. If a batch contains multiple upgrade programs whose pre-requisites have been executed, these programs are started based on their runtime class.
- Batch
-
The batch to which the upgrade program belongs.
- Real Run Status
-
The real status of the upgrade step.
- Server Number
-
The actual server (bshell) where the upgrade program was executed.
- Result Description
-
A short description of the result of the upgrade program's execution.
- Number of Restarts
-
The number of times the upgrade program was started before it succeeded.
- Attention Needed
-
If this check box is selected, the upgrade task requires additional actions, although it may have succeeded.
- Physical Company
-
The physical company for which the program was executed. This field is filled if the upgrade program did not have to run for the company specified in the Company field.
- First Start Date
-
The date and time the upgrade program was executed for the first time.
- Last Start Date
-
The date and time the upgrade program was executed for the last time.
- Last Failure Date
-
The date and time the last failure occurred during execution of the upgrade program.
- Completion Date
-
The date and time the Real Run Status of the upgrade program was set to Completed.
- Release Date
-
The date and time the upgrade program succeeded.
- Simulation Run Status
-
The simulation status of the upgrade step.
- Server Number
-
The actual server (bshell) where the upgrade program was executed.
- Result Description
-
A short description of the result of the upgrade program's execution.
- Number of Restarts
-
The number of times the upgrade program was started before it succeeded.
- Attention Needed
-
If this check box is selected, the upgrade task requires additional actions, although it may have succeeded.
- Physical Company
-
The physical company for which the program was executed. This field is filled if the upgrade program did not have to run for the company specified in the Company field.
- First Start Date
-
The date and time the upgrade program was executed for the first time.
- Last Start Date
-
The date and time the upgrade program was executed for the last time.
- Last Failure Date
-
The date and time the last failure occurred during execution of the upgrade program.
- Completion Date
-
The date and time the Real Run Status of the upgrade program was set to Completed.
- Release Date
-
The date and time the upgrade program succeeded.