Manufacturing

Project Activity Progress widget (PCS)

This new widget is used to graphically display information about the execution progress of project (PCS) activities.

For project activities, this period data is shown in a chart:

  • Count of started activities
  • Completed on time
  • Completed too late
  • Not finished, but should be finished

Data is displayed based on company, employee, and role as selected in the Configure widget.

Job Shop Planning Board

A planning board for scheduling has been added to facilitate the day-to-day activities of a planner.

These features are supported:

  • Filtering based on work center, shop floor planner and routing group.
  • For a selected production order or operation, display of material availability based on pegging information. Short or late supply is indicated by self-explanatory color coding.
  • Functions to perform actions directly from the planning board, such as creating a new production order and completing an operation.
  • Display of linked orders and operations in the production and scheduling Gantt charts.