Service Costing Break Hierarchy and Search Path
The project, element and activity are retrieved from the Costing Breaks (tppdm3600m000) session. LN follows hierarchy for the various cost types, based on the following attributes.
Material Resource Lines Costing Breaks - Service Material (tppdm3103m000).
- Installation Group of the MWO Header
- Item of the MWO header (main item)
- Item of the material line
- Serial Number of the material line item
- Project of the material line item
The following search order is applied:
- Material line item and serial number
- Main item and material line item
- Material line item
- Installation group and main item
- Main item
- Installation group
- Service item group
Labor Resource Lines Costing Breaks - Service Labor (tppdm3104m000).
- Master Routing of the MWO Activity the labor line is linked to
- Routing Options of the MWO Activity the labor line is linked to
- Reference Activity of the labor line
- Task of the labor line
- Project of the labor line
The following search order is applied:
- Reference activity and task
- Task
- Reference activity
- Master routing, routing option and reference activity
- Master routing and routing option
- Master routing
Other Resource Lines Costing Breaks - Service Other Cost (tppdm3105m000).
- Cost Type (Tooling / Subcontracting / Other)
- Item Group of the cost line item
- Item
- Serial Number
- Project of the cost line
The following search order is applied:
If cost type is tooling
- (Tool) Item and (Tool) serial number
- (Tool) item
If cost type is subcontracting
- Item
- Item group
If cost type is other
- Item
- Item group